Route 1 construction in Thomaston nearing end

Oct 09, 2017

Thomaston — The Thomaston Route 1 project is nearing completion, with Main Street paving expected to be finished by the end of October, according to the Department of Transportation. DOT expects sidewalk and lawn repair work to continue through December.

One-way traffic has resumed on Route 1, in accordance with the contract between DOT and Lane Construction. Lane Construction will work hard to keep traffic flowing and use one-way traffic on an as needed base particularly when it is unsafe to use two-way traffic, according to Thomaston officials.

The following is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Work areas may change as needed. Drivers are advised to use caution when navigating the work zones.

Monday, Oct. 9

• Raise Manholes – Georges St / Booker St

• Finegrade Basins – Oyster River Rd to Wadsworth St

• Excavate & Gravel Sidewalks – Wadsworth St to School St

Tuesday, Oct. 10

• Raise Manholes – Water Tower Rd / Ship St / Shibles Ln

• Pave Curb & Basins & Drives – Oyster River Rd to Green St

Wednesday, Oct. 11

• Pave Surface – Georges St to Gilchrest St

All Beechwood Street traffic will be directed down Erin Street. All Knox Street traffic will be directed down Thatcher Street.

Thursday, Oct. 12

• Pave Surface – Georges St to Gilchrest St

All Beechwood Street traffic will be directed down Erin Street. All Knox Street traffic will be directed down Thatcher Street.

• Pave Surface – Turn Lane Southbound Pine St to St George’s Rd

Friday, Oct. 13

• Pave Surface Sideroads – Beechwood St to Fish St

• Loam – Toll Bridge Rd to Ridgeview Dr

Saturday, Oct. 14

• Pave Surface Sideroads – School St to Gilchrest St

Monday, Oct. 16

• Pave Surface – Shibles Ln to Booker St

Tuesday, Oct. 17

• Pave Surface – Shibles Ln to Booker St

Wednesday, Oct. 18

• Pave Surface – Thomaston Auction Gallery to Shibles Ln

• Excavation & Gravel Sidewalks – Wadsworth St to Booker St

Thursday, Oct. 19

• Pave Surface – Thomaston Auction Gallery to Shibles Ln

• Pave Surface – Oyster River Rd to Ridgeview Dr

• Excavation & Gravel Sidewalks – Wadsworth St to Booker St

Friday, Oct. 20

• Pave Sideroads – Shibles Ln to Georges St

• Excavation & Gravel Sidewalks – Green St to Booker St

Saturday, Oct. 21

• Pave Sideroads – Toll Bridge Rd to Ship St