Thomaston — This is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Be advised work areas may change as needed. Please use caution when navigating the work zones.

Monday, June 19

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Form & Place Concrete Sidewalks – Green Street to Beechwood Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

• Loam – Pine Street to Riverside Drive

Tuesday, June 20

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

Wednesday, June 21

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

• Excavate and Gravel Driveways – Shibles Lane to Ship Street

• Set Basin Frame and Cover – Business at Gilchrest Street

Thursday, June 22

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

• Excavate and Gravel Driveways – Shibles Lane to Ship Street

Friday, June 23

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

• Excavate and Gravel Driveways – Shibles Lane to Ship Street

Monday, June 26

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Prep Curb Areas for Pavement – Green Street to Fish Street

Tuesday, June 27

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Pave Curb Areas – Green Street to Fish Street

Wednesday, June 28

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Pave Curb Areas – Green Street to Fish Street

Thursday, June 29

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Pave Curb Areas – Green Street to Fish Street

Friday, June 30

• Common Excavation & Gravel – Ship Street to Wadsworth Street

• Pave Curb Areas – Green Street to Fish Street

Two-Way Traffic

Beginning on Monday, two-way traffic will return.

New Sidewalks

Work is being done to complete the sidewalks on the east end of the project. In some places temporarily, there are uneven areas between the new sidewalks and driveways.

Questions or Concerns

Questions, problems, or concerns may be directed to Audrey Lovering at audreylovering@gmail.com or 899-6925.