Continued Route 1 construction outlined

Nov 17, 2017
Photo by: Beth A. Birmingham Road work continues on Atlantic Highway in Thomaston Nov. 18.

Thomaston — The Maine Department of Transportation has announced the following work schedule for the Thomaston Route 1 project for Nov. 20 through Dec. 2.

The schedule may change due to weather, scheduling of subcontractors, and other unknown conditions. Work areas may change as needed. Drivers are advised to use caution when navigating the work zones.

Monday, Nov. 20

- Finegrade Sidewalks, Ship Street to Wadsworth Street

- Pave Sidewalks, Green Street to Gilchrest Street

- Pave Driveways, Toll Bridge Road to Oyster River Road

- Loam, Beechwood Street to Gilchrest Street

- Prep Concrete Walkways, Green Street to Pine Street

- Install Precast Detectable Warning Fields, Shibles Lane to School Street

Tuesday, Nov. 21

- Finegrade Sidewalks, Shibles Lane to Water Tower Road

- Pave Sidewalks, Wadsworth Street to Green Street

- Pave Driveways, Green Street to Fish Street

- Loam, Beechwood Street to Gilchrest Street

- Pavement Hand Striping, Toll Bridge Road to Fish Street

- Place Concrete Walkways, Green Street to Pine Street

- Install Precast Detectable Warning Fields, Shibles Lane to School Street

Wednesday, Nov. 22

- Finegrade Sidewalks, Shibles Lane to Water Tower Road

- Pave Sidewalks, Wadsworth Street to Green Street

- Pave Misc Walks & Drives, Shibles Lane to Fish Street

- Loam, Booker Street to Green Street

Thursday, Nov. 23

- No work; Thanksgiving holiday

Friday, Nov. 24

- No work; Thanksgiving holiday

Monday, Nov. 27

- Finegrade Sidewalks, Ridgeview Drive to Ship Street

- Pave Sidewalks, Wadsworth Street to Green Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Loam, Wadsworth Street to Green Street

Tuesday, Nov. 28

- Finegrade Sidewalks, Ridgeview Drive to Ship Street

- Pave Sidewalks, Shibles Lane to Wadsworth Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Loam, Wadsworth Street to Green Street

Wednesday, Nov. 29

- Finegrade Sidewalks, Ridgeview Drive to Ship Street

- Pave Sidewalks, Shibles Lane to Wadsworth Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Loam, Wadsworth Street to Green Street

Thursday, Nov. 30

- Back up Gravel Drives, Toll Bridge Road to Fish Street

- Pave Sidewalks, Shibles Lane to Wadsworth Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Loam, Wadsworth Street to Green Street

Friday, Dec. 1

- Back up Gravel Drives, Toll Bridge Road to Fish Street

- Pave Sidewalks, Ridgeview Lane to Ship Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Loam, Ship Street to Wadsworth Street

Saturday, Dec. 2

- Back up Gravel Drives, Toll Bridge Road to Fish Street

- Install/Reset Signs, Toll Bridge Road to Fish Street

- Pave Sidewalks, Ridgeview Lane to Ship Street

For more information, contact Audrey Lovering at audreylovering@gmail.com or 899-6925.