Below is an estimated schedule for work to be continued on Route 1 in Thomaston from Nov. 6 through Nov. 18.

The schedule may change due to weather, scheduling of subcontractors, and other unknown conditions. Be advised work areas may change as needed. Drivers are advised to use caution when navigating the work zones.

Monday, Nov. 6

• Finegrade Sidewalks – Beechwood Street to Erin Street

• Excavate Driveway – Adjacent to Post Office

Tuesday, Nov. 7

• Finegrade Sidewalks – Beechwood Street to Erin Street

• Finegrade Sidewalks – Booker Street to Beechwood Street

• Backup Curb – Ridgeview to Ship Street

• Pavement Hand Striping – Toll Bridge Road to Fish Street

Wednesday, Nov. 8

• Finegrade Sidewalks – Booker Street to Beechwood Street

• Backup Curb – Ridgeview to Ship Street

Thursday, Nov. 9

• Finegrade Sidewalks – Booker Street to Beechwood Street

• Backup Curb – Ship Street to Wadsworth Street

Friday, Nov. 10

• Backup Curb/Loam – School Street to Green Street

• Pavement Striping – Toll Bridge Road to Fish Street

Saturday, Nov. 11: No work — Veteran's Day

Monday, Nov. 13

• Finegrade Sidewalks – Wadsworth Street to Booker Street

• Backfill Curb/Loam – School Street to Green Street

Tuesday, Nov. 14

• Finegrade Sidewalks – Ship Street to Wadsworth Street

• Backfill Curb/ Loam – School Street to Green Street

• Pave Sidewalks – Main Mall Road to Gilchrest Street

Wednesday, Nov. 15

• Finegrade Sidewalks – Shibles Lane to Ship Street

• Backfill Curb/Loam – Oyster River Road to Ridgeview Drive

• Pave Sidewalks – Wadsworth Street to Main Mall Road

Thursday, Nov. 16

• Backfill Curb/Loam – Oyster River Road to Shibles Lane

• Finegrade Sidewalks – Shibles Lane to Ship Street

• Pave Sidewalks – Wadsworth Street to Main Mall Road

Friday, Nov. 17

• Backfill Curb/Loam – Ship Street to Wadsworth Street

• Finegrade Sidewalks – Oyster River Road to Shibles Lane

• Pave Sidewalks – Wadsworth Street to Main Mall Road

Saturday, Nov. 18

• Finegrade Sidewalks – Shibles Lane to Ship Street

• Pave Sidewalks – Wadsworth Street to Main Mall Road

The end is near

The MaineDOT Route 1 project in Thomaston is coming to a close. All paving for this project will be completed in 2017.

In the spring of 2018, Lane will return to Thomaston to tend to areas damaged by winter weather, such as loam, reseeding areas that did not grow and other small finish-up items.

For more information, contact Audrey Lovering at audreylovering@gmail.com or 899-6925.