The following is an estimated schedule that may change due to weather, scheduling of subcontractors, and other unknown conditions. Be advised work areas may change as needed. Drivers are urged to use caution when navigating the work zones.

Tuesday, May 23

• Common Excavation & Gravel – Oyster River Road to Toll Bridge Road

• Install Traffic Signals – Beechwood Street & Knox Street

• Finegrade Gravel – Shibles Lane to Oyster River Road

• Repair Concrete – James Griffith Bridge

Wednesday, May 24

• Common Excavation & Gravel in Bump Outs – Green Street. to Knox St.reet

• Install Traffic Signals – Beechwood Street and Knox Street

• Finegrade Gravel – Shibles Lane to Oyster River Road

• Repair Concrete – James Griffith Bridge

Thursday, May 25

• Install Traffic Signals – Beechwood Street and Knox Street

• Pave 19mm Base Pavement – Shibles Lane to Oyster River Road

• Repair Concrete – James Griffith Bridge

Friday, May 26

• Install Traffic Signals – Beechwood Street and Knox Street

• Repair Concrete – James Griffith Bridge

• Off road by noon

Monday, May 29

• No work — Memorial Day

Tuesday, May 30

• Common Excavation & Gravel – Oyster River Road to Toll Bridge Road

• Mill Pavement – Shibles Lane to Ship Street

• Granite Curb – Green Street to Gilchrest Street

• Finegrade Sidewalks – Roxbury Street to Fish Street

• Install Membrane – James Griffith Bridge

Wednesday, May 31

• Common Excavation & Gravel – Oyster River Road to Toll Bridge Road

• Sawcut Concrete – Shibles Lane to Ship Street

• Granite Curb – Beechwood Street to Pine Street

• Finegrade Sidewalks – Roxbury Street to Fish Street

• Pave Bridge Phase III – James Griffith Bridge

Thursday, June 1

• Common Excavation & Gravel – Oyster River Road to Toll Bridge Road

• Gravel Curb Areas – Green Street to Gilchrest Street

• Sawcut Concrete – Shibles Lane to Ship Street

• Finegrade Gravel – Oyster River Road to Toll Bridge Road

• Remove Barrier and Temp Striping – James Griffith Bridge

Friday, June 2

• Common Excavation & Gravel – Oyster River Road to Toll Bridge Road

• Gravel Curb Areas – Green Street to Gilchrest Street

• Finegrade Gravel Curb Areas – Green Street to Gilchrest Street

• Finegrade Gravel – Oyster River Road to Toll Bridge Road

• Sawcut Concrete – Shibles Lane to Ship Street

• Pave Bridge Surface – James Griffith Bridge

Saturday, June 3

• Pave 19mm Base Pavement – Oyster River Road to Toll Bridge Road

• Finegrade Gravel Curb Areas – Green Street to Gilchrest Street

Project Information / Q & A

Post office/131 Main St. paving and painted for parking: The last biweekly update mentioned the parking spaces returning in front of the post office. Current work schedule for this part of the project: the entrance to the post office will be base paved in the next week or two. Mainline Surface Paving intends to be completed before June 19, when two-way traffic will be maintained. The parking stalls in front of the post office will be striped once the surface paving has been placed.

Questions or Concerns

Contact Audrey Lovering with questions or concerns at audreylovering@gmail.com or 899-6925.